| Action Date | Action Description | 
|---|---|
| Sep 02, 2011 | Assent Application Received | 
| Sep 02, 2011 | Administrative Review for Completeness | 
| Sep 06, 2011 | Team Review for Completeness | 
| Sep 06, 2011 | Team Review for Completeness | 
| Sep 06, 2011 | Application Accepted | 
| Sep 13, 2011 | Additional Information Received | 
| Sep 16, 2011 | Additional Information Received | 
| Sep 30, 2011 | Additional Information Received | 
| Oct 03, 2011 | Biologist Report | 
| Oct 03, 2011 | Engineering Report | 
| Oct 04, 2011 | Typist for Processing | 
| Oct 05, 2011 | Executive Sign Off | 
| Oct 05, 2011 | Sent to Photo Copy | 
| Oct 06, 2011 | Permit Approved | 
| Oct 29, 2011 | Historical Preservation Conditional Approval | 
| Nov 03, 2011 | Plans Received | 
| Feb 13, 2012 | Commencement of Work Notice received | 
| Apr 10, 2012 | Modification Request | 
| Apr 10, 2012 | Administrative Review for Completeness | 
| Apr 10, 2012 | Team Review for Completeness | 
| Apr 10, 2012 | Team Review for Completeness | 
| Apr 12, 2012 | Biologist Report | 
| Apr 12, 2012 | Engineering Report | 
| Apr 18, 2012 | Modification Approved | 
| May 22, 2012 | Historical Preservation Conditional Approval |