| Action Date | Action Description | 
|---|---|
| Dec 22, 2011 | Team Review for Completeness | 
| Dec 22, 2011 | Buffer Zone Management Application Received | 
| Dec 22, 2011 | Administrative Review for Completeness | 
| Dec 23, 2011 | Team Review for Completeness | 
| Dec 23, 2011 | Application Accepted | 
| Jan 04, 2012 | HPHC Historical Preservation No Effect | 
| Mar 20, 2012 | 30-Day Notification of Cancellation letter | 
| Apr 17, 2012 | Correspondence Received | 
| Apr 18, 2012 | Additional Information Requested from Applicant | 
| May 22, 2012 | Additional Information Received | 
| Aug 02, 2012 | 30-Day Notification of Cancellation letter | 
| Aug 13, 2012 | Certified Receipt Received | 
| Aug 31, 2012 | Additional Information Received | 
| Oct 26, 2012 | Additional Information Requested from Applicant | 
| May 16, 2013 | Additional Information Received | 
| May 21, 2013 | Additional Information Received | 
| Jul 08, 2013 | Additional Information Received | 
| Aug 13, 2013 | Biologist Report | 
| Aug 13, 2013 | Engineering Report | 
| Aug 14, 2013 | Permit Approved | 
| Aug 14, 2013 | Typist for Processing | 
| Aug 28, 2013 | Executive Sign Off | 
| Aug 28, 2013 | Sent to Photo Copy | 
| Sep 12, 2013 | Land Evidence Date | 
| Oct 21, 2013 | Commencement of Work Notice received |