| Action Date | Action Description | 
|---|---|
| Feb 14, 2012 | Assent Application Received | 
| Feb 14, 2012 | Administrative Review for Completeness | 
| Feb 16, 2012 | Team Review for Completeness | 
| Feb 16, 2012 | Team Review for Completeness | 
| Feb 16, 2012 | Application Accepted | 
| Feb 28, 2012 | HPHC Historical Preservation No Effect | 
| Mar 06, 2012 | 30 day Public Notice Issued | 
| Apr 06, 2012 | Public Notice End Date | 
| May 15, 2012 | Additional Information Received | 
| Jul 09, 2012 | Additional Information Received | 
| Jul 23, 2012 | US Army Corps of Engineers Approval Received | 
| Jul 31, 2012 | Category A* (Docks) | 
| Jul 31, 2012 | Biologist Report | 
| Jul 31, 2012 | Engineering Report | 
| Aug 01, 2012 | Permit Approved | 
| Aug 01, 2012 | Typist for Processing | 
| Aug 02, 2012 | Executive Sign Off | 
| Aug 02, 2012 | Sent to Photo Copy | 
| Aug 03, 2012 | Land Evidence Date |