| Action Date | Action Description | 
|---|---|
| Jan 09, 2013 | Assent Application Received | 
| Jan 09, 2013 | Administrative Review for Completeness | 
| Jan 24, 2013 | Team Review for Completeness | 
| Jan 24, 2013 | Team Review for Completeness | 
| Jan 24, 2013 | Deficient Application - Owner Notification Sent | 
| Feb 14, 2013 | Deficient Application Picked Up | 
| Apr 23, 2013 | Deficiency Response Received | 
| Apr 29, 2013 | Team Review for Completeness | 
| Apr 29, 2013 | Team Review for Completeness | 
| Apr 29, 2013 | Application Accepted | 
| May 06, 2013 | HPHC Historical Preservation No Effect | 
| May 17, 2013 | 30 day Public Notice Issued | 
| Jun 14, 2013 | Objections/Comments Received | 
| Jun 17, 2013 | Objections/Comments Received | 
| Jun 17, 2013 | Public Notice End Date | 
| Jun 18, 2013 | Objections/Comments Received | 
| Jul 01, 2013 | Objections/Comments Received | 
| Jul 18, 2013 | Correspondence Received | 
| Sep 16, 2013 | Additional Information Received | 
| Oct 02, 2013 | Objections/Comments Received | 
| Oct 30, 2013 | Biologist Report | 
| Oct 30, 2013 | Engineering Report | 
| Oct 30, 2013 | Supervisor Engineer SignOff | 
| Nov 04, 2013 | Supervisor Biologist SignOff | 
| Nov 06, 2013 | Executive Signoff of Staff Reports | 
| Dec 16, 2013 | Ready to Schedule Semi-Monthly Meeting | 
| Dec 16, 2013 | Mail Agenda Notice | 
| Jan 02, 2014 | Additional Information Received | 
| Jan 09, 2014 | Correspondence Received | 
| Jan 14, 2014 | Council Approval Granted | 
| Jan 14, 2014 | Semi-Monthly Meeting Date Scheduled | 
| Jan 14, 2014 | Semi-Monthly Meeting Held | 
| Jan 28, 2014 | 30 Day Appeal Notification to Owner | 
| Jan 28, 2014 | Legal Response/Decision | 
| Mar 05, 2014 | Stipulation Package from Biologist | 
| Mar 06, 2014 | Stipulation Package by Engineer | 
| Mar 10, 2014 | Typist for Processing | 
| Mar 10, 2014 | Permit Approved | 
| Mar 11, 2014 | Executive Sign Off | 
| Mar 11, 2014 | Sent to Photo Copy | 
| Mar 24, 2014 | Land Evidence Date | 
| May 07, 2014 | US Army Corps of Engineers Approval Received | 
| Jun 13, 2014 | Land Evidence Date | 
| Aug 28, 2014 | Assent Correction Request Received | 
| Aug 29, 2014 | Assent Correction Mailed | 
| Sep 10, 2014 | Land Evidence Date | 
| Jun 17, 2015 | Note to File |