| Action Date | Action Description | 
|---|---|
| Feb 13, 2013 | Assent Application Received | 
| Feb 13, 2013 | Administrative Review for Completeness | 
| Feb 13, 2013 | Team Review for Completeness | 
| Feb 13, 2013 | Application Accepted | 
| Feb 17, 2013 | HPHC Historical Preservation No Effect | 
| Mar 13, 2013 | Joint Public Notice | 
| Apr 05, 2013 | Additional Information Received | 
| Apr 13, 2013 | Public Notice End Date | 
| Apr 30, 2013 | Plans Received | 
| May 07, 2013 | Additional Information Received | 
| May 21, 2013 | Engineering Report | 
| May 21, 2013 | Biologist Report | 
| May 21, 2013 | Engineering Report | 
| May 23, 2013 | Mail Agenda Notice | 
| May 23, 2013 | Executive Signoff of Staff Reports | 
| May 28, 2013 | Semi-Monthly Meeting Date Scheduled | 
| May 28, 2013 | Water Quality Certification | 
| May 28, 2013 | Council Approval Granted | 
| May 28, 2013 | Semi-Monthly Meeting Held | 
| May 30, 2013 | Stipulation Package from Biologist | 
| Jun 05, 2013 | Stipulation Package by Engineer | 
| Jun 25, 2013 | Legal Response/Decision | 
| Jun 25, 2013 | US Army Corps of Engineers Approval Received | 
| Jun 25, 2013 | Under Review/Decision | 
| Jun 25, 2013 | 30 Day Appeal Notification to Owner | 
| Jun 26, 2013 | Permit Approved | 
| Jun 26, 2013 | Typist for Processing | 
| Jun 27, 2013 | Executive Sign Off | 
| Jun 27, 2013 | Sent to Photo Copy | 
| Jul 25, 2013 | US Army Corps of Engineers Approval Received |