| Action Date | Action Description | 
|---|---|
| Jan 05, 2015 | Assent Application Received | 
| Jan 05, 2015 | Administrative Review for Completeness | 
| Jan 06, 2015 | Team Review for Completeness | 
| Jan 06, 2015 | Application Accepted | 
| Jan 20, 2015 | Entry of Appearance Received | 
| Jan 22, 2015 | Correspondence Received | 
| Jan 22, 2015 | Correspondence Received | 
| Jan 28, 2015 | 30 day Public Notice Issued | 
| Feb 02, 2015 | HPHC Historical Preservation No Effect | 
| Feb 28, 2015 | Public Notice End Date | 
| Mar 13, 2015 | Public Notice End Date Extension Granted | 
| Mar 16, 2015 | Correspondence Received | 
| Mar 19, 2015 | Objections/Comments Received | 
| Mar 20, 2015 | Engineering Report | 
| Mar 23, 2015 | Biologist Report | 
| Mar 26, 2015 | Permit Approved | 
| Mar 26, 2015 | Typist for Processing | 
| Mar 27, 2015 | Executive Sign Off | 
| Mar 27, 2015 | Sent to Photo Copy | 
| Mar 27, 2015 | Public Notice End Date Extension Granted | 
| Apr 13, 2015 | Land Evidence Date |