| Action Date | Action Description | 
|---|---|
| Jul 22, 2016 | Assent Application Received | 
| Jul 25, 2016 | Administrative Review for Completeness | 
| Jul 26, 2016 | Team Review for Completeness | 
| Jul 26, 2016 | Application Accepted | 
| Aug 09, 2016 | Biologist Report | 
| Aug 10, 2016 | Typist for Processing | 
| Aug 15, 2016 | Executive Sign Off | 
| Aug 15, 2016 | Sent to Photo Copy | 
| Aug 15, 2016 | Permit Approved | 
| Aug 17, 2016 | HPHC Historical Preservation No Effect | 
| Oct 13, 2016 | Land Evidence Date | 
| Jan 09, 2017 | Modification Request | 
| Jan 09, 2017 | Administrative Review for Completeness | 
| Jan 10, 2017 | Team Review for Completeness | 
| Jan 23, 2017 | Biologist Report | 
| Jan 23, 2017 | Typist for Processing | 
| Jan 23, 2017 | Executive Sign Off | 
| Jan 23, 2017 | Sent to Photo Copy | 
| Jan 23, 2017 | Modification Approved | 
| Feb 03, 2017 | HPHC Historical Preservation No Effect |