| Action Date | Action Description | 
|---|---|
| Apr 11, 2017 | Assent Application Received | 
| Apr 11, 2017 | Administrative Review for Completeness | 
| Apr 11, 2017 | Team Review for Completeness | 
| Apr 11, 2017 | Application Accepted | 
| Apr 28, 2017 | Plans Received | 
| May 05, 2017 | Biologist Report | 
| May 10, 2017 | HPHC Historical Preservation Comments/Concerns | 
| Jun 19, 2017 | Typist for Processing | 
| Jun 19, 2017 | Executive Sign Off | 
| Jun 19, 2017 | Sent to Photo Copy | 
| Jun 19, 2017 | Permit Approved | 
| Jul 05, 2017 | Land Evidence Date | 
| Mar 16, 2018 | Modification Request | 
| Mar 16, 2018 | Administrative Review for Completeness | 
| Mar 16, 2018 | Team Review for Completeness | 
| Mar 16, 2018 | Application Accepted | 
| Mar 23, 2018 | Biologist Report | 
| Mar 26, 2018 | Typist for Processing | 
| Mar 26, 2018 | Executive Sign Off | 
| Mar 26, 2018 | Sent to Photo Copy | 
| Mar 26, 2018 | Modification Approved | 
| Apr 30, 2018 | Land Evidence Date |