| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 05, 2017 | Assent Application Received | 
| May 08, 2017 | Administrative Review for Completeness | 
| May 10, 2017 | Team Review for Completeness | 
| May 10, 2017 | Team Review for Completeness | 
| May 10, 2017 | Application Accepted | 
| May 15, 2017 | Correspondence Mailed/Faxed/E-mailed | 
| Jun 05, 2017 | HPHC Historical Preservation No Effect | 
| Jun 12, 2017 | Plans Received | 
| Jun 12, 2017 | 30 day Public Notice Issued | 
| Jul 11, 2017 | Objections/Comments Received | 
| Jul 12, 2017 | Public Notice End Date | 
| Jul 21, 2017 | Public Notice End Date Extension Granted | 
| Jul 24, 2017 | Objections/Comments Received | 
| Sep 01, 2017 | Additional Information Requested from Applicant | 
| Oct 16, 2017 | Plans Received | 
| Nov 07, 2017 | Supervisor Biologist SignOff | 
| Nov 10, 2017 | Supervisor Engineer SignOff | 
| Nov 30, 2017 | Executive Signoff of Staff Reports | 
| Dec 01, 2017 | Biologist Report | 
| Jun 15, 2018 | Ready to Schedule Semi-Monthly Meeting | 
| Jun 15, 2018 | Mail Agenda Notice | 
| Jun 26, 2018 | Council Approval Granted | 
| Jun 26, 2018 | Semi-Monthly Meeting Date Scheduled | 
| Aug 08, 2018 | Stipulation Package from Biologist | 
| Aug 08, 2018 | Legal Response/Decision | 
| Aug 14, 2018 | Typist for Processing | 
| Aug 14, 2018 | Executive Sign Off | 
| Aug 14, 2018 | Sent to Photo Copy | 
| Aug 14, 2018 | Permit Approved | 
| Sep 11, 2018 | Land Evidence Date | 
| Nov 01, 2018 | Assent Requirement |