| Action Date | Action Description | 
|---|---|
| Jul 13, 2017 | Freshwater Wetland - Preliminary Determination | 
| Jul 14, 2017 | Administrative Review for Completeness | 
| Jul 20, 2017 | Team Review for Completeness | 
| Jul 20, 2017 | Application Accepted | 
| Jul 26, 2017 | Additional Information Requested from Applicant | 
| Aug 01, 2017 | HPHC Historical Preservation No Effect | 
| Aug 01, 2017 | Additional Information Requested from Applicant | 
| Aug 11, 2017 | Plans Received | 
| Aug 31, 2017 | Meeting Held | 
| Oct 06, 2017 | Plans Received | 
| Oct 11, 2017 | Biologist Report | 
| Oct 16, 2017 | Typist for Processing | 
| Oct 16, 2017 | Executive Sign Off | 
| Oct 16, 2017 | Sent to Photo Copy | 
| Oct 16, 2017 | Permit Approved | 
| Oct 27, 2017 | Land Evidence Date | 
| Mar 30, 2018 | Modification Request | 
| Mar 30, 2018 | Administrative Review for Completeness | 
| Apr 03, 2018 | Team Review for Completeness | 
| Apr 03, 2018 | Application Accepted | 
| Apr 11, 2018 | HPHC Historical Preservation No Effect | 
| May 03, 2018 | Biologist Report | 
| May 03, 2018 | Plans Received | 
| May 07, 2018 | Typist for Processing | 
| May 07, 2018 | Executive Sign Off | 
| May 07, 2018 | Sent to Photo Copy | 
| May 07, 2018 | Modification Approved | 
| May 25, 2018 | Land Evidence Date |