| Action Date | Action Description | 
|---|---|
| Dec 07, 2017 | Assent Application Received | 
| Dec 07, 2017 | Administrative Review for Completeness | 
| Dec 18, 2017 | Team Review for Completeness | 
| Dec 18, 2017 | Application Accepted | 
| Dec 28, 2017 | Biologist Report | 
| Dec 29, 2017 | Typist for Processing | 
| Dec 29, 2017 | Executive Sign Off | 
| Dec 29, 2017 | Sent to Photo Copy | 
| Dec 29, 2017 | Permit Approved | 
| Jan 26, 2018 | HPHC Historical Preservation No Effect | 
| Feb 09, 2018 | Land Evidence Date |