| Action Date | Action Description |
|---|---|
| Mar 28, 2018 | Assent Application Received |
| Aug 14, 2018 | Administrative Review for Completeness |
| Aug 15, 2018 | Team Review for Completeness |
| Aug 15, 2018 | Application Accepted |
| Aug 16, 2018 | Category A* (Docks) |
| Aug 23, 2018 | 30 day Public Notice Issued |
| Aug 27, 2018 | HPHC Historical Preservation No Effect |
| Sep 04, 2018 | Additional Information Received |
| Sep 17, 2018 | Objections/Comments Received |
| Sep 18, 2018 | Objections/Comments Received |
| Sep 20, 2018 | Additional Information Requested from Applicant |
| Sep 21, 2018 | Objections/Comments Received |
| Sep 23, 2018 | Public Notice End Date |
| Sep 24, 2018 | Additional Information Received |
| Oct 19, 2018 | Objections/Comments Received |
| Dec 06, 2018 | Additional Information Requested from Applicant |
| Jan 02, 2019 | Plans Received |
| Feb 11, 2019 | Biologist Report |
| Feb 15, 2019 | Supervisor Biologist SignOff |
| Feb 22, 2019 | Supervisor Engineer SignOff |
| Feb 22, 2019 | Executive Signoff of Staff Reports |
| Feb 28, 2019 | Ready to Schedule Semi-Monthly Meeting |
| Feb 28, 2019 | Mail Agenda Notice |
| Mar 04, 2019 | Continuance Requested |
| Mar 04, 2019 | Continuance request by applicant granted by Director |
| Mar 12, 2019 | Semi-Monthly Meeting Date Scheduled |
| Mar 28, 2019 | Ready to Schedule Semi-Monthly Meeting |
| Mar 29, 2019 | Mail Agenda Notice |
| Apr 08, 2019 | Objections/Comments Received |
| Apr 09, 2019 | Council Approval Granted |
| Apr 09, 2019 | Semi-Monthly Meeting Date Scheduled |
| Jul 31, 2019 | Under Review/Decision |
| Jul 31, 2019 | Legal Response/Decision |
| Jul 31, 2019 | Typist for Processing |
| Jul 31, 2019 | Executive Sign Off |
| Jul 31, 2019 | Sent to Photo Copy |
| Jul 31, 2019 | Permit Approved |
| Aug 01, 2019 | Stipulation Package from Biologist |
| Aug 05, 2019 | Land Evidence Date |
| Aug 05, 2019 | Land Evidence Date |
| May 27, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Nov 09, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Jan 08, 2024 | Modification Request |
| Jan 26, 2024 | Administrative Review for Completeness |
| Feb 02, 2024 | Bio Team Review for Completeness |
| Feb 02, 2024 | Project Manager |
| Feb 02, 2024 | Application Accepted |
| Feb 20, 2024 | HPHC Historical Preservation No Effect |
| Feb 26, 2024 | Additional Information Requested from Applicant |
| Feb 26, 2024 | Additional Information Received |
| Mar 29, 2024 | 30 day Public Notice Issued |
| Apr 29, 2024 | Public Notice End Date |
| Aug 28, 2024 | Biologist Report |
| Sep 13, 2024 | Typist for Processing |
| Sep 13, 2024 | Executive Sign Off |
| Sep 13, 2024 | Sent to Photo Copy |
| Sep 13, 2024 | Modification Approved |
| Sep 13, 2024 | Modification mailed |
| Sep 13, 2024 | Modification mailed |
| Oct 31, 2024 | Land Evidence Date |