| Action Date | Action Description | 
|---|---|
| Oct 30, 2018 | Assent Application Received | 
| Oct 30, 2018 | Administrative Review for Completeness | 
| Nov 02, 2018 | Team Review for Completeness | 
| Nov 02, 2018 | Application Accepted | 
| Nov 19, 2018 | 30 day Public Notice Issued | 
| Nov 27, 2018 | HPHC Historical Preservation No Effect | 
| Dec 19, 2018 | Public Notice End Date | 
| Feb 11, 2019 | Typist for Processing | 
| Feb 11, 2019 | Engineering Report | 
| Aug 07, 2019 | Modification Request | 
| Aug 07, 2019 | Administrative Review for Completeness | 
| Aug 19, 2019 | Team Review for Completeness | 
| Aug 19, 2019 | Application Accepted | 
| Sep 06, 2019 | HPHC Review Pending | 
| Sep 06, 2019 | HPHC Historical Preservation No Effect | 
| Oct 28, 2019 | Modification Approved | 
| Oct 28, 2019 | Engineering Report | 