| Action Date | Action Description | 
|---|---|
| Nov 25, 2019 | Assent Application Received | 
| Nov 25, 2019 | Administrative Review for Completeness | 
| Dec 06, 2019 | Bio Team Review for Completeness | 
| Dec 06, 2019 | Eng Team Review for Completeness | 
| Dec 06, 2019 | Application Accepted | 
| Feb 17, 2020 | Joint Public Notice | 
| Feb 18, 2020 | HPHC Review Pending | 
| Feb 18, 2020 | HPHC Historical Preservation No Effect | 
| Mar 16, 2020 | Letter of Support for Project | 
| Mar 16, 2020 | Letter of Support for Project | 
| Mar 17, 2020 | Public Notice End Date | 
| Jun 05, 2020 | Additional Information Received | 
| Jun 19, 2020 | Letter of Support for Project | 
| Aug 12, 2020 | Letter of Support for Project | 
| Aug 18, 2020 | Additional Information Received | 
| Sep 24, 2020 | Water Quality Certification | 
| Sep 29, 2020 | Ready to Schedule Semi-Monthly Meeting | 
| Sep 29, 2020 | Mail Agenda Notice | 
| Oct 02, 2020 | Engineering Report | 
| Oct 06, 2020 | Biologist Report | 
| Oct 13, 2020 | Semi-Monthly Meeting Date Scheduled | 
| Oct 19, 2020 | Council Approval Granted | 
| Oct 27, 2020 | Stipulation Package by Engineer | 
| Oct 27, 2020 | Typist for Processing | 
| Oct 27, 2020 | Executive Sign Off | 
| Oct 27, 2020 | Sent to Photo Copy | 
| Oct 27, 2020 | Permit Approved | 
| Nov 03, 2020 | Land Evidence Date | 
| Apr 07, 2023 | Comments Received | 
| Aug 28, 2023 | Extension of Permit Request | 
| Nov 29, 2023 | Enforcement Compliance Inspection Required | 
| Dec 01, 2023 | Process Extension | 
| Dec 01, 2023 | Typist for Processing | 
| Dec 01, 2023 | Executive Sign Off | 
| Dec 01, 2023 | Sent to Photo Copy | 
| Dec 01, 2023 | Extension Approved | 
| May 05, 2025 | Correspondence Received | 
| May 05, 2025 | Correspondence Received | 
| May 13, 2025 | Correspondence Mailed/Faxed/E-mailed | 
| May 16, 2025 | Correspondence Received | 
| May 16, 2025 | Additional Information Received |