| Action Date | Action Description | 
|---|---|
| Nov 25, 2019 | Assent Application Received | 
| Nov 26, 2019 | Administrative Review for Completeness | 
| Nov 26, 2019 | Bio Team Review for Completeness | 
| Dec 06, 2019 | Eng Team Review for Completeness | 
| Dec 06, 2019 | Application Accepted | 
| Dec 06, 2019 | Category B assigned | 
| Jan 07, 2020 | HPHC Historical Preservation No Effect | 
| Jan 07, 2020 | HPHC Review Pending | 
| Feb 13, 2020 | 30 day Public Notice Issued | 
| Mar 13, 2020 | Public Notice End Date | 
| Jun 05, 2020 | Executive Signoff of Staff Reports | 
| Jun 05, 2020 | Ready to Schedule Semi-Monthly Meeting | 
| Jun 05, 2020 | Engineering Report | 
| Jun 05, 2020 | Additional Information Received | 
| Jun 09, 2020 | Mail Agenda Notice | 
| Jun 23, 2020 | Council Approval Granted | 
| Jun 23, 2020 | Semi-Monthly Meeting Date Scheduled | 
| Jun 25, 2020 | Typist for Processing | 
| Jun 25, 2020 | Permit Approved | 
| Jun 25, 2020 | Stipulation Package by Engineer | 
| Jun 25, 2020 | Legal Response/Decision | 
| Aug 12, 2020 | Land Evidence Date | 
| Sep 24, 2020 | US Army Corps of Engineers Approval Received | 
| Nov 17, 2020 | Modification Request | 
| Nov 19, 2020 | Administrative Review for Completeness | 
| Nov 23, 2020 | Bio Team Review for Completeness | 
| Dec 07, 2020 | Eng Team Review for Completeness | 
| Dec 09, 2020 | Stipulation Package by Engineer | 
| Dec 09, 2020 | Typist for Processing | 
| Dec 09, 2020 | Executive Sign Off | 
| Dec 09, 2020 | Sent to Photo Copy | 
| Dec 09, 2020 | Modification Approved | 
| Dec 09, 2020 | Engineering Report | 
| Dec 23, 2020 | HPHC Historical Preservation No Effect | 
| Dec 23, 2020 | HPHC Review Pending | 
| Jun 16, 2021 | Duplicate Original Assent requested/mailed | 
| Jun 23, 2021 | Land Evidence Date |