| Action Date | Action Description | 
|---|---|
| Jan 07, 2020 | Assent Application Received | 
| Jan 07, 2020 | Administrative Review for Completeness | 
| Jan 14, 2020 | Additional Information Received | 
| Jan 15, 2020 | Application Accepted | 
| Jan 15, 2020 | Bio Team Review for Completeness | 
| Jan 21, 2020 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 27, 2020 | Plans Received | 
| Feb 25, 2020 | HPHC Historical Preservation No Effect | 
| Feb 25, 2020 | HPHC Review Pending | 
| Feb 26, 2020 | Additional Information Received | 
| Mar 03, 2020 | Biologist Report | 
| Mar 04, 2020 | Typist for Processing | 
| Mar 04, 2020 | Executive Sign Off | 
| Mar 04, 2020 | Sent to Photo Copy | 
| Mar 04, 2020 | Permit Approved | 
| Mar 30, 2020 | Land Evidence Date |