| Action Date | Action Description | 
|---|---|
| Jan 14, 2020 | Assent Application Received | 
| Jan 14, 2020 | Administrative Review for Completeness | 
| Jan 15, 2020 | Bio Team Review for Completeness | 
| Jan 15, 2020 | Application Accepted | 
| Jan 15, 2020 | Category A* (Docks) | 
| Jan 28, 2020 | HPHC Review Pending | 
| Jan 28, 2020 | HPHC Historical Preservation No Effect | 
| Feb 06, 2020 | 30 day Public Notice Issued | 
| Mar 06, 2020 | Public Notice End Date | 
| Mar 10, 2020 | Comments Received | 
| Mar 16, 2020 | Dock Meeting -- Approval | 
| Mar 25, 2020 | Typist for Processing | 
| Mar 25, 2020 | Executive Sign Off | 
| Mar 25, 2020 | Sent to Photo Copy | 
| Mar 25, 2020 | Permit Approved | 
| Mar 25, 2020 | Biologist Report | 
| Mar 31, 2020 | Land Evidence Date | 
| Apr 09, 2020 | Dock Post-Construction Certification by Engineer received. | 
| Jun 24, 2021 | Modification Request | 
| Jun 30, 2021 | Administrative Review for Completeness | 
| Jul 06, 2021 | Bio Team Review for Completeness | 
| Jul 06, 2021 | Application Accepted | 
| Jul 06, 2021 | Project Manager | 
| Jul 21, 2021 | HPHC Historical Preservation No Effect | 
| Jul 21, 2021 | HPHC Review Pending | 
| Aug 31, 2021 | 30 day Public Notice Issued | 
| Sep 30, 2021 | Public Notice End Date | 
| Oct 14, 2021 | Dock Meeting -- Approval | 
| Oct 15, 2021 | Stipulation Package from Biologist | 
| Oct 15, 2021 | Biologist Report | 
| Nov 04, 2021 | Typist for Processing | 
| Nov 04, 2021 | Executive Sign Off | 
| Nov 04, 2021 | Sent to Photo Copy | 
| Nov 04, 2021 | Modification Approved | 
| Dec 01, 2021 | Land Evidence Date |