| Action Date | Action Description | 
|---|---|
| Feb 18, 2020 | Assent Application Received | 
| Feb 18, 2020 | Administrative Review for Completeness | 
| Feb 26, 2020 | Eng Team Review for Completeness | 
| Feb 26, 2020 | Application Accepted | 
| Mar 06, 2020 | Project Manager | 
| Mar 17, 2020 | Typist for Processing | 
| Mar 17, 2020 | Executive Sign Off | 
| Mar 17, 2020 | Sent to Photo Copy | 
| Mar 17, 2020 | Permit Approved | 
| Mar 17, 2020 | Engineering Report | 
| Apr 13, 2020 | Land Evidence Date | 
| May 15, 2020 | HPHC Historical Preservation Comments/Concerns | 
| May 15, 2020 | HPHC Review Pending | 
| Dec 28, 2020 | Modification Request | 
| Dec 30, 2020 | Administrative Review for Completeness | 
| Jan 08, 2021 | Eng Team Review for Completeness | 
| Jan 21, 2021 | Engineering Report | 
| Jan 21, 2021 | Stipulation Package by Engineer | 
| Jan 21, 2021 | CHA -- application modified due to CHA info | 
| Jan 21, 2021 | Modification Approved | 
| Jan 21, 2021 | Typist for Processing | 
| Jan 21, 2021 | Executive Sign Off | 
| Jan 21, 2021 | Sent to Photo Copy | 
| Jan 21, 2021 | HPHC Historical Preservation No Effect | 
| Jan 21, 2021 | HPHC Review Pending | 
| Jan 28, 2021 | Land Evidence Date |