| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jul 09, 2020 | Assent Application Received | 
| Jul 10, 2020 | Administrative Review for Completeness | 
| Aug 05, 2020 | Category A* (Docks) | 
| Aug 05, 2020 | Eng Team Review for Completeness | 
| Aug 05, 2020 | Application Accepted | 
| Aug 05, 2020 | Project Manager | 
| Aug 06, 2020 | 30 day Public Notice Issued | 
| Sep 04, 2020 | HPHC Review Pending | 
| Sep 04, 2020 | HPHC Historical Preservation No Effect | 
| Sep 04, 2020 | Objections/Comments Received | 
| Sep 06, 2020 | Public Notice End Date | 
| Sep 21, 2020 | Entry of Appearance Received | 
| Dec 09, 2020 | Comments Received | 
| Feb 08, 2021 | Additional Information Received | 
| May 19, 2021 | Additional Information Received | 
| Sep 20, 2023 | Additional Information Received | 
| Nov 07, 2023 | Additional Information Received | 
| Nov 15, 2023 | Additional Information Received | 
| Nov 15, 2023 | Engineering Report | 
| Nov 17, 2023 | Ready to Schedule Semi-Monthly Meeting | 
| Nov 20, 2023 | Mail Agenda Notice | 
| Nov 28, 2023 | Council Approval Granted | 
| Nov 28, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Jan 29, 2025 | Legal Response/Decision | 
| Feb 27, 2025 | Plans Received | 
| Mar 26, 2025 | Stipulation Package by Engineer | 
| Mar 31, 2025 | Typist for Processing | 
| Mar 31, 2025 | Executive Sign Off | 
| Mar 31, 2025 | Sent to Photo Copy | 
| Mar 31, 2025 | Permit Approved | 
| Apr 03, 2025 | Permit Mailed | 
| Apr 14, 2025 | Assent Correction Request Received | 
| Apr 24, 2025 | Land Evidence Date |