| Action Date | Action Description | 
|---|---|
| Apr 05, 2021 | Assent Application Received | 
| Apr 12, 2021 | Administrative Review for Completeness | 
| Apr 16, 2021 | Bio Team Review for Completeness | 
| Apr 16, 2021 | Application Accepted | 
| Apr 17, 2021 | Project Manager | 
| Apr 17, 2021 | Category A* (Docks) | 
| May 06, 2021 | 30 day Public Notice Issued | 
| Jun 06, 2021 | Public Notice End Date | 
| Jun 17, 2021 | Dock Meeting -- Approval | 
| Jul 07, 2021 | HPHC Historical Preservation No Effect | 
| Jul 07, 2021 | HPHC Review Pending | 
| Jul 13, 2021 | Biologist Report | 
| Jul 13, 2021 | Stipulation Package from Biologist | 
| Jul 19, 2021 | Typist for Processing | 
| Jul 19, 2021 | Executive Sign Off | 
| Jul 19, 2021 | Sent to Photo Copy | 
| Jul 19, 2021 | Permit Approved | 
| Jul 22, 2021 | Permit Mailed | 
| Jul 28, 2021 | Land Evidence Date | 
| Mar 01, 2023 | Dock Post-Construction Certification by Engineer received. |