| Action Date | Action Description | 
|---|---|
| Sep 24, 2021 | Assent Application Received | 
| Sep 28, 2021 | Administrative Review for Completeness | 
| Sep 28, 2021 | CHA Worksheet received | 
| Sep 29, 2021 | Bio Team Review for Completeness | 
| Oct 05, 2021 | Bio Team Review for Completeness | 
| Oct 05, 2021 | Deficient Application - Owner Notification Sent | 
| Oct 05, 2021 | Plans Received | 
| Oct 06, 2021 | Deficient Application Picked Up | 
| Oct 22, 2021 | Deficiency Response Received | 
| Oct 25, 2021 | Bio Team Review for Completeness | 
| Oct 25, 2021 | Application Accepted | 
| Oct 26, 2021 | Project Manager | 
| Nov 15, 2021 | Plans Received | 
| Nov 17, 2021 | HPHC Historical Preservation No Effect | 
| Nov 17, 2021 | HPHC Review Pending | 
| Aug 08, 2022 | Plans Received | 
| Aug 22, 2022 | Biologist Report | 
| Aug 23, 2022 | Permit Mailed | 
| Aug 23, 2022 | Sent to Photo Copy | 
| Aug 23, 2022 | Typist for Processing | 
| Aug 23, 2022 | Executive Sign Off | 
| Aug 23, 2022 | Permit Approved | 
| Sep 06, 2022 | Land Evidence Date | 
| Mar 31, 2025 | Extension of Permit Request | 
| Jul 08, 2025 | Enforcement Compliance Inspection Required | 
| Jul 11, 2025 | Process Extension | 
| Jul 11, 2025 | Extension Approved |