| Action Date | Action Description | 
|---|---|
| Jan 28, 2021 | Executive Sign Off | 
| Nov 05, 2021 | Assent Application Received | 
| Nov 10, 2021 | Administrative Review for Completeness | 
| Nov 10, 2021 | CHA Worksheet received | 
| Nov 17, 2021 | Eng Team Review for Completeness | 
| Nov 17, 2021 | Application Accepted | 
| Nov 17, 2021 | Project Manager | 
| Nov 30, 2021 | HPHC Review Pending | 
| Nov 30, 2021 | HPHC Historical Preservation No Effect | 
| Dec 28, 2021 | Typist for Processing | 
| Dec 28, 2021 | Engineering Report | 
| Dec 28, 2021 | Sent to Photo Copy | 
| Dec 28, 2021 | Permit Approved | 
| Jan 05, 2022 | Permit Mailed | 
| Jan 12, 2023 | Land Evidence Date | 
| Oct 10, 2024 | Extension of Permit Request | 
| Aug 21, 2025 | Enforcement Compliance Inspection Required | 
| Aug 22, 2025 | Process Extension | 
| Aug 22, 2025 | Extension Approved |