| Action Date | Action Description | 
|---|---|
| Nov 24, 2021 | Maintenance Certification Request | 
| Nov 29, 2021 | Administrative Review for Completeness | 
| Dec 07, 2021 | Bio Team Review for Completeness | 
| Dec 07, 2021 | Application Accepted | 
| Dec 09, 2021 | Project Manager | 
| Dec 15, 2021 | HPHC Review Pending | 
| Dec 15, 2021 | HPHC Historical Preservation No Effect | 
| Jan 24, 2022 | Additional Information Requested from Applicant | 
| Jan 27, 2022 | Correspondence Received | 
| Feb 21, 2022 | Biologist Report | 
| Mar 01, 2022 | Typist for Processing | 
| Mar 01, 2022 | Executive Sign Off | 
| Mar 01, 2022 | Sent to Photo Copy | 
| Mar 01, 2022 | Permit Mailed | 
| Mar 01, 2022 | Permit Approved |