| Action Date | Action Description | 
|---|---|
| Feb 22, 2022 | Assent Application Received | 
| Mar 02, 2022 | Administrative Review for Completeness | 
| Mar 02, 2022 | Bio Team Review for Completeness | 
| Mar 02, 2022 | Application Accepted | 
| Mar 07, 2022 | Project Manager | 
| Mar 07, 2022 | Bio Team Review for Completeness | 
| Mar 24, 2022 | HPHC Review Pending | 
| Mar 24, 2022 | HPHC Historical Preservation No Effect | 
| Apr 06, 2022 | Objections/Comments Received | 
| Apr 07, 2022 | Objections/Comments Received | 
| Apr 11, 2022 | Objections/Comments Received | 
| Apr 11, 2022 | Objections/Comments Received | 
| Apr 11, 2022 | Objections/Comments Received | 
| Apr 14, 2022 | Objections/Comments Received | 
| Apr 15, 2022 | Note to File | 
| Apr 19, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 25, 2022 | Comments Received | 
| May 27, 2022 | Correspondence Received | 
| Aug 23, 2022 | Note to File | 
| Nov 29, 2022 | Additional Information Received | 
| Dec 16, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 03, 2023 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 03, 2023 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 12, 2023 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 13, 2023 | Objection withdrawal received | 
| Jan 13, 2023 | Correspondence Received | 
| Jan 20, 2023 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 20, 2023 | Objection withdrawal received | 
| Jan 20, 2023 | Objection withdrawal received | 
| Jan 23, 2023 | Objection withdrawal received | 
| Jan 23, 2023 | Objection withdrawal received | 
| Feb 02, 2023 | Permit Approved | 
| Feb 02, 2023 | Biologist Report | 
| Oct 20, 2023 | Land Evidence Date |