| Action Date | Action Description | 
|---|---|
| Jul 19, 2022 | Assent Application Received | 
| Oct 25, 2022 | Administrative Review for Completeness | 
| Oct 25, 2022 | Deficient Application - Owner Notification Sent | 
| Oct 31, 2022 | Deficiency Response Received | 
| Nov 09, 2022 | Bio Team Review for Completeness | 
| Nov 09, 2022 | Application Accepted | 
| Nov 15, 2022 | Project Manager | 
| Dec 13, 2022 | HPHC Historical Preservation No Effect | 
| Mar 21, 2023 | Plans Received | 
| Apr 18, 2023 | Engineering Report | 
| May 08, 2023 | Typist for Processing | 
| May 08, 2023 | Executive Sign Off | 
| May 08, 2023 | Sent to Photo Copy | 
| May 08, 2023 | Permit Approved | 
| May 09, 2023 | Permit Mailed | 
| Oct 13, 2023 | Land Evidence Date |