| Action Date | Action Description | 
|---|---|
| Jul 18, 2022 | Assent Application Received | 
| Aug 01, 2022 | Administrative Review for Completeness | 
| Aug 15, 2022 | Eng Team Review for Completeness | 
| Aug 15, 2022 | Application Accepted | 
| Aug 15, 2022 | Project Manager | 
| Sep 06, 2022 | HPHC Historical Preservation No Effect | 
| Oct 18, 2022 | Engineering Report | 
| Oct 24, 2022 | Typist for Processing | 
| Oct 24, 2022 | Executive Sign Off | 
| Oct 24, 2022 | Sent to Photo Copy | 
| Oct 24, 2022 | Permit Approved | 
| Oct 24, 2022 | Permit Mailed | 
| Jan 26, 2023 | Land Evidence Date |