| Action Date | Action Description | 
|---|---|
| Jan 30, 2023 | Maintenance Certification Request | 
| Jan 31, 2023 | Administrative Review for Completeness | 
| Feb 08, 2023 | Eng Team Review for Completeness | 
| Feb 08, 2023 | Project Manager | 
| Feb 08, 2023 | Application Accepted | 
| Feb 17, 2023 | HPHC Historical Preservation No Effect | 
| Feb 20, 2023 | Engineering Report | 
| Mar 02, 2023 | Typist for Processing | 
| Mar 02, 2023 | Executive Sign Off | 
| Mar 02, 2023 | Sent to Photo Copy | 
| Mar 02, 2023 | Permit Approved | 
| Mar 03, 2023 | Permit Mailed | 
| Mar 08, 2023 | Commencement of Work Notice received | 
| Mar 23, 2023 | Land Evidence Date |