| Action Date | Action Description | 
|---|---|
| Feb 06, 2023 | HPHC Historical Preservation No Effect | 
| Feb 06, 2023 | Dredge Application | 
| Feb 13, 2023 | Administrative Review for Completeness | 
| Apr 28, 2023 | Eng Team Review for Completeness | 
| Apr 28, 2023 | Application Accepted | 
| Apr 28, 2023 | Project Manager | 
| Nov 29, 2023 | Engineering Report | 
| Dec 04, 2023 | Typist for Processing | 
| Dec 04, 2023 | Permit Approved | 
| Dec 06, 2023 | Permit Mailed | 
| Dec 15, 2023 | Land Evidence Date | 
| Jan 27, 2025 | Letter of Authorization | 
| Feb 13, 2025 | Additional Information Received | 
| Mar 12, 2025 | Letter of Authorization | 
| Apr 01, 2025 | Correspondence Received | 
| Apr 07, 2025 | Correspondence Received |