| Action Date | Action Description | 
|---|---|
| Feb 08, 2023 | Assent Application Received | 
| Feb 14, 2023 | Administrative Review for Completeness | 
| Feb 15, 2023 | Bio Team Review for Completeness | 
| Feb 15, 2023 | Project Manager | 
| Feb 15, 2023 | Application Accepted | 
| Mar 20, 2023 | HPHC Historical Preservation No Effect | 
| Mar 29, 2023 | Additional Information Requested from Applicant | 
| Nov 28, 2023 | Additional Information Received | 
| Nov 29, 2023 | Typist for Processing | 
| Nov 29, 2023 | Executive Sign Off | 
| Nov 29, 2023 | Sent to Photo Copy | 
| Nov 29, 2023 | Permit Approved | 
| Nov 29, 2023 | Biologist Report | 
| Dec 04, 2023 | Permit Mailed | 
| Oct 07, 2024 | Duplicate Original Assent requested/mailed | 
| Oct 17, 2024 | Land Evidence Date |