| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Mar 24, 2023 | Assent Application Received | 
| Mar 27, 2023 | Administrative Review for Completeness | 
| Mar 30, 2023 | Bio Team Review for Completeness | 
| Apr 07, 2023 | Application Accepted | 
| Apr 07, 2023 | Project Manager | 
| Apr 07, 2023 | Eng Team Review for Completeness | 
| Apr 11, 2023 | HPHC Historical Preservation No Effect | 
| Apr 25, 2023 | 30 day Public Notice Issued | 
| May 25, 2023 | Public Notice End Date | 
| Jun 21, 2023 | Engineering Report | 
| Jun 21, 2023 | Mail Agenda Notice | 
| Jun 22, 2023 | Executive Signoff of Staff Reports | 
| Jun 27, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Aug 28, 2023 | Mail Agenda Notice | 
| Sep 12, 2023 | Council Approval Granted | 
| Sep 12, 2023 | Semi-Monthly Meeting Date Scheduled | 
| Sep 28, 2023 | Stipulation Package by Engineer | 
| Oct 25, 2023 | Legal Response/Decision | 
| Oct 25, 2023 | 30 Day Appeal Notification to Owner | 
| Nov 30, 2023 | US Army Corp of Engineers Permit Date | 
| Dec 05, 2023 | Typist for Processing | 
| Dec 05, 2023 | Executive Sign Off | 
| Dec 05, 2023 | Sent to Photo Copy | 
| Dec 05, 2023 | Permit Approved | 
| Dec 07, 2023 | Permit Mailed | 
| Oct 22, 2024 | Land Evidence Date |