| Action Date | Action Description | 
|---|---|
| Jun 07, 2023 | Maintenance Certification Request | 
| Jun 09, 2023 | Administrative Review for Completeness | 
| Jun 26, 2023 | Eng Team Review for Completeness | 
| Jun 26, 2023 | Project Manager | 
| Jun 26, 2023 | Application Accepted | 
| Jul 11, 2023 | HPHC Historical Preservation No Effect | 
| Aug 02, 2023 | Additional Information Received | 
| Oct 05, 2023 | Additional Information Received | 
| Oct 23, 2023 | Biologist Report | 
| Oct 23, 2023 | Engineering Report | 
| Oct 26, 2023 | Typist for Processing | 
| Oct 26, 2023 | Executive Sign Off | 
| Oct 26, 2023 | Sent to Photo Copy | 
| Oct 26, 2023 | Permit Approved | 
| Nov 01, 2023 | Permit Mailed | 
| Nov 30, 2023 | Land Evidence Date | 
| Dec 15, 2023 | Note to File |