| Action Date | Action Description | 
|---|---|
| Aug 11, 2023 | Freshwater Wetlands Application - New - received | 
| Aug 16, 2023 | Administrative Review for Completeness | 
| Aug 29, 2023 | Bio Team Review for Completeness | 
| Aug 29, 2023 | Application Accepted | 
| Aug 29, 2023 | Project Manager | 
| Sep 25, 2023 | HPHC Historical Preservation No Effect | 
| Oct 03, 2023 | Biologist Report | 
| Oct 05, 2023 | Typist for Processing | 
| Oct 05, 2023 | Executive Sign Off | 
| Oct 05, 2023 | Sent to Photo Copy | 
| Oct 05, 2023 | Permit Approved | 
| Oct 06, 2023 | Permit Mailed | 
| Oct 25, 2023 | Land Evidence Date | 
| Nov 22, 2023 | Commencement of Work Notice received |