| Action Date | Action Description |
|---|---|
| Biologist Report | |
| Sep 22, 2023 | Freshwater Wetlands Application - New - received |
| Sep 27, 2023 | Administrative Review for Completeness |
| Nov 02, 2023 | Bio Team Review for Completeness |
| Nov 02, 2023 | Application Accepted |
| Nov 29, 2023 | HPHC Historical Preservation No Effect |
| Jan 23, 2024 | Objections/Comments Received |
| Feb 12, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Feb 12, 2024 | Correspondence Received |
| Mar 01, 2024 | Comments Received |
| May 14, 2024 | Correspondence Received |
| Jun 18, 2024 | Correspondence Received |
| Jun 21, 2024 | Additional Information Requested from Applicant |
| Jun 21, 2024 | Phone Call |
| Jun 27, 2024 | Additional Information Received |
| Jul 08, 2024 | 30 day Public Notice Issued |
| Jul 09, 2024 | Comments Received |
| Jul 22, 2024 | Objections/Comments Received |
| Aug 02, 2024 | Objections/Comments Received |
| Aug 02, 2024 | Objections/Comments Received |
| Aug 05, 2024 | Objections/Comments Received |
| Aug 05, 2024 | Objections/Comments Received |
| Aug 07, 2024 | Objections/Comments Received |
| Aug 07, 2024 | Objections/Comments Received |
| Aug 08, 2024 | Objections/Comments Received |
| Aug 08, 2024 | Public Notice End Date |
| Aug 09, 2024 | Objections/Comments Received |
| Aug 21, 2024 | Correspondence Received |
| Aug 21, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Sep 11, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Sep 26, 2024 | Meeting Held |
| Sep 26, 2024 | Plans Received |
| Oct 09, 2024 | Note to File |
| Feb 05, 2025 | Additional Information Received |
| Mar 07, 2025 | 30 day Public Notice Issued |
| Mar 10, 2025 | Objections/Comments Received |
| Mar 19, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Mar 19, 2025 | Correspondence Received |
| Mar 27, 2025 | US Army Corps of Engineers Project Number received. |
| Apr 02, 2025 | Objections/Comments Received |
| Apr 02, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Apr 03, 2025 | Objections/Comments Received |
| Apr 04, 2025 | Objections/Comments Received |
| Apr 04, 2025 | Objections/Comments Received |
| Apr 07, 2025 | Objections/Comments Received |
| Apr 07, 2025 | Public Notice End Date |
| Apr 08, 2025 | Correspondence Mailed/Faxed/E-mailed |
| Apr 24, 2025 | Objections/Comments Received |
| Apr 25, 2025 | Public Notice End Date Extension Granted |
| May 08, 2025 | Correspondence Received |
| Jun 16, 2025 | Correspondence Received |
| Jun 20, 2025 | Correspondence Mailed/Faxed/E-mailed |