| Action Date | Action Description | 
|---|---|
| Oct 10, 2023 | Assent Application Received | 
| Oct 13, 2023 | Administrative Review for Completeness | 
| Oct 18, 2023 | Bio Team Review for Completeness | 
| Oct 25, 2023 | Deficient Application - Owner Notification Sent | 
| Dec 09, 2024 | Deficiency Response Received | 
| Jan 16, 2025 | Bio Team Review for Completeness | 
| Jan 16, 2025 | Application Accepted | 
| Jan 16, 2025 | Project Manager | 
| Jan 22, 2025 | Biologist Report | 
| Jan 27, 2025 | Plans Received | 
| Feb 13, 2025 | HPHC Historical Preservation No Effect | 
| Feb 18, 2025 | Permit Approved | 
| Feb 18, 2025 | Executive Sign Off | 
| Feb 18, 2025 | Sent to Photo Copy | 
| Feb 18, 2025 | Typist for Processing | 
| Feb 26, 2025 | Permit Mailed | 
| Mar 06, 2025 | Land Evidence Date |