| Action Date | Action Description | 
|---|---|
| Nov 01, 2023 | Assent Application Received | 
| Nov 03, 2023 | Administrative Review for Completeness | 
| Nov 08, 2023 | Bio Team Review for Completeness | 
| Nov 08, 2023 | Application Accepted | 
| Nov 08, 2023 | Project Manager | 
| Dec 08, 2023 | HPHC Historical Preservation No Effect | 
| Jan 23, 2024 | Additional Information Requested from Applicant | 
| Jan 24, 2024 | CHA Worksheet received | 
| Jan 31, 2024 | Biologist Report | 
| Feb 01, 2024 | Typist for Processing | 
| Feb 01, 2024 | Executive Sign Off | 
| Feb 01, 2024 | Sent to Photo Copy | 
| Feb 01, 2024 | Permit Approved | 
| Feb 05, 2024 | Permit Mailed | 
| Feb 15, 2024 | Land Evidence Date | 
| Sep 19, 2024 | Commencement of Work Notice received |