| Action Date | Action Description | 
|---|---|
| Land Evidence Date | |
| Jan 12, 2024 | Assent Application Received | 
| Jan 12, 2024 | CHA Worksheet received | 
| Jan 23, 2024 | Bio Team Review for Completeness | 
| Jan 23, 2024 | Application Accepted | 
| Jan 23, 2024 | Project Manager | 
| Jan 23, 2024 | Administrative Review for Completeness | 
| Feb 07, 2024 | HPHC Historical Preservation No Effect | 
| Feb 09, 2024 | Biologist Report | 
| Feb 16, 2024 | Typist for Processing | 
| Feb 16, 2024 | Executive Sign Off | 
| Feb 16, 2024 | Sent to Photo Copy | 
| Feb 16, 2024 | Permit Approved | 
| Feb 20, 2024 | Permit Mailed | 
| Mar 04, 2024 | Land Evidence Date | 
| Mar 18, 2024 | Commencement of Work Notice received | 
| Oct 03, 2024 | Modification Request | 
| Oct 15, 2024 | Administrative Review for Completeness | 
| Oct 15, 2024 | Bio Team Review for Completeness | 
| Oct 15, 2024 | Application Accepted | 
| Oct 15, 2024 | Biologist Report | 
| Oct 16, 2024 | Typist for Processing | 
| Oct 16, 2024 | Executive Sign Off | 
| Oct 16, 2024 | Sent to Photo Copy | 
| Oct 16, 2024 | Modification Approved | 
| Oct 17, 2024 | Modification mailed | 
| Oct 23, 2024 | HPHC Historical Preservation No Effect |