| Action Date | Action Description | 
|---|---|
| Jan 18, 2024 | Maintenance Certification Request | 
| Jan 23, 2024 | Administrative Review for Completeness | 
| Feb 12, 2024 | Eng Team Review for Completeness | 
| Feb 12, 2024 | Deficient Application - Owner Notification Sent | 
| Apr 17, 2025 | Deficiency Response Received | 
| May 20, 2025 | Application Accepted | 
| May 20, 2025 | Engineering Report | 
| May 22, 2025 | HPHC Historical Preservation No Effect | 
| Jun 02, 2025 | Permit Approved | 
| Jun 06, 2025 | Permit Mailed | 
| Jun 24, 2025 | Commencement of Work Notice received |