| Action Date | Action Description | 
|---|---|
| Assent Requirement | |
| May 13, 2024 | Assent Application Received | 
| May 13, 2024 | CHA Worksheet received | 
| May 15, 2024 | Administrative Review for Completeness | 
| Jun 03, 2024 | Bio Team Review for Completeness | 
| Jun 06, 2024 | Deficient Application - Owner Notification Sent | 
| Jun 12, 2024 | Correspondence Received | 
| Jun 13, 2024 | Correspondence Mailed/Faxed/E-mailed | 
| Jul 05, 2024 | Deficiency Response Received | 
| Jul 15, 2024 | Bio Team Review for Completeness | 
| Jul 15, 2024 | Application Accepted | 
| Jul 15, 2024 | Project Manager | 
| Aug 07, 2024 | HPHC Historical Preservation No Effect | 
| Aug 21, 2024 | Biologist Report | 
| Aug 22, 2024 | Typist for Processing | 
| Aug 22, 2024 | Executive Sign Off | 
| Aug 22, 2024 | Sent to Photo Copy | 
| Aug 22, 2024 | Permit Approved | 
| Aug 26, 2024 | Permit Mailed | 
| Sep 11, 2024 | Land Evidence Date |