| Action Date | Action Description | 
|---|---|
| Jul 22, 2024 | Maintenance Certification Request | 
| Jul 24, 2024 | Administrative Review for Completeness | 
| Aug 08, 2024 | Eng Team Review for Completeness | 
| Aug 08, 2024 | Deficient Application - Owner Notification Sent | 
| Aug 14, 2024 | Deficient Application Picked Up | 
| Oct 16, 2024 | Deficiency Response Received | 
| Oct 23, 2024 | Bio Team Review for Completeness | 
| Oct 23, 2024 | Eng Team Review for Completeness | 
| Oct 23, 2024 | Application Accepted | 
| Oct 23, 2024 | Project Manager | 
| Oct 24, 2024 | Additional Information Received | 
| Oct 30, 2024 | HPHC Historical Preservation No Effect | 
| Nov 27, 2024 | Plans Received | 
| Dec 06, 2024 | Biologist Report | 
| Dec 06, 2024 | Engineering Report | 
| Dec 09, 2024 | Typist for Processing | 
| Dec 10, 2024 | Executive Sign Off | 
| Dec 10, 2024 | Sent to Photo Copy | 
| Dec 10, 2024 | Permit Approved | 
| Dec 11, 2024 | Permit Mailed | 
| Dec 30, 2024 | Land Evidence Date | 
| Jan 22, 2025 | Commencement of Work Notice received |