| Action Date | Action Description | 
|---|---|
| Jan 24, 2025 | Assent Application Received | 
| Jan 31, 2025 | Administrative Review for Completeness | 
| Feb 03, 2025 | Additional Information Received | 
| Feb 11, 2025 | Application Accepted | 
| Feb 11, 2025 | Bio Team Review for Completeness | 
| Feb 11, 2025 | Project Manager | 
| Feb 13, 2025 | Additional Information Received | 
| Feb 17, 2025 | Plans Received | 
| Feb 18, 2025 | CHA Worksheet received | 
| Mar 17, 2025 | HPHC Historical Preservation No Effect | 
| Mar 17, 2025 | Biologist Report | 
| Mar 27, 2025 | Typist for Processing | 
| Mar 27, 2025 | Assent Requirement | 
| Mar 27, 2025 | Executive Sign Off | 
| Mar 27, 2025 | Sent to Photo Copy | 
| Mar 27, 2025 | Permit Approved | 
| Mar 31, 2025 | Permit Mailed | 
| Apr 02, 2025 | Land Evidence Date |