| Action Date | Action Description | 
|---|---|
| May 12, 2025 | Assent Application Received | 
| May 15, 2025 | Administrative Review for Completeness | 
| May 16, 2025 | Bio Team Review for Completeness | 
| May 16, 2025 | Project Manager | 
| May 16, 2025 | Application Accepted | 
| May 30, 2025 | Biologist Report | 
| Jun 03, 2025 | Typist for Processing | 
| Jun 03, 2025 | Executive Sign Off | 
| Jun 03, 2025 | Sent to Photo Copy | 
| Jun 03, 2025 | Permit Approved | 
| Jun 06, 2025 | Permit Mailed | 
| Jun 16, 2025 | Commencement of Work Notice received | 
| Jun 16, 2025 | Land Evidence Date | 
| Jul 07, 2025 | HPHC Historical Preservation No Effect |