| Action Date | Action Description | 
|---|---|
| Jun 12, 1995 | Application Accepted | 
| Jul 19, 1995 | Engineering Report | 
| Aug 01, 1995 | Permit Approved | 
| Aug 01, 1995 | Land Evidence Date | 
| Jan 19, 2017 | Modification Request | 
| Jan 20, 2017 | Administrative Review for Completeness | 
| Jan 24, 2017 | Team Review for Completeness | 
| Jan 24, 2017 | Application Accepted | 
| Feb 02, 2017 | 30 day Public Notice Issued | 
| Feb 20, 2017 | HPHC Historical Preservation No Effect | 
| Mar 04, 2017 | Public Notice End Date | 
| Mar 23, 2018 | Dock Meeting -- Approval | 
| May 02, 2018 | Plans Received | 
| May 08, 2018 | Biologist Report | 
| May 08, 2018 | Typist for Processing | 
| May 08, 2018 | Executive Sign Off | 
| May 08, 2018 | Sent to Photo Copy | 
| May 08, 2018 | Modification Approved | 
| May 29, 2018 | US Army Corps of Engineers Approval Received | 
| Jun 04, 2018 | Land Evidence Date |