| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jul 12, 1995 | Application Accepted | 
| Aug 07, 1995 | Biologist Report | 
| Aug 08, 1995 | Permit Approved | 
| Aug 08, 1995 | Land Evidence Date | 
| Apr 19, 2021 | Modification Request | 
| Apr 20, 2021 | Administrative Review for Completeness | 
| Apr 22, 2021 | Bio Team Review for Completeness | 
| Apr 26, 2021 | Deficient Application - Owner Notification Sent | 
| May 04, 2021 | Deficient Application Picked Up | 
| Nov 24, 2021 | Modification Request | 
| Nov 29, 2021 | Administrative Review for Completeness | 
| Nov 30, 2021 | Category A* (Docks) | 
| Nov 30, 2021 | Bio Team Review for Completeness | 
| Nov 30, 2021 | Project Manager | 
| Dec 09, 2021 | HPHC Historical Preservation No Effect | 
| Dec 09, 2021 | HPHC Review Pending | 
| Jan 13, 2022 | 30 day Public Notice Issued | 
| Feb 07, 2022 | Plans Received | 
| Feb 11, 2022 | Dock Meeting -- Approval | 
| Feb 13, 2022 | Public Notice End Date | 
| Feb 17, 2022 | Biologist Report | 
| Feb 18, 2022 | US Army Corp of Engineers Permit Date | 
| Feb 22, 2022 | Executive Sign Off | 
| Feb 22, 2022 | Sent to Photo Copy | 
| Feb 22, 2022 | Modification Approved | 
| Feb 22, 2022 | Typist for Processing | 
| Feb 24, 2022 | Permit Mailed | 
| Sep 24, 2024 | Land Evidence Date |