| Action Date | Action Description | 
|---|---|
| Apr 14, 2005 | Freshwater Wetland - Preliminary Determination | 
| Apr 15, 2005 | Administrative Review for Completeness | 
| Apr 22, 2005 | Team Review for Completeness | 
| Apr 22, 2005 | Application Accepted | 
| May 03, 2005 | HPHC Review Pending | 
| Jun 11, 2005 | Biologist Report | 
| Jun 16, 2005 | Typist for Processing | 
| Jun 16, 2005 | Executive Sign Off | 
| Jun 16, 2005 | Sent to Photo Copy | 
| Jun 16, 2005 | Permit Approved | 
| Aug 25, 2005 | Assent Correction Request Received | 
| Aug 25, 2005 | Typist for Processing | 
| Aug 25, 2005 | Executive Sign Off | 
| Aug 25, 2005 | Sent to Photo Copy | 
| Aug 25, 2005 | Assent Correction Mailed | 
| Sep 01, 2005 | Typist for Processing | 
| Sep 01, 2005 | Executive Sign Off | 
| Sep 01, 2005 | Sent to Photo Copy | 
| Sep 02, 2005 | Land Evidence Date | 
| Jun 01, 2006 | Commencement of Work Notice received |