| Action Date | Action Description | 
|---|---|
| Feb 01, 2006 | Assent Application Received | 
| Feb 01, 2006 | Administrative Review for Completeness | 
| Feb 09, 2006 | Deficient Application - Owner Notification Sent | 
| Mar 01, 2006 | Deficiency Response Received | 
| Mar 02, 2006 | Team Review for Completeness | 
| May 08, 2006 | Application Accepted | 
| May 09, 2006 | Engineering Report | 
| May 09, 2006 | Typist for Processing | 
| May 09, 2006 | Executive Sign Off | 
| May 09, 2006 | Sent to Photo Copy | 
| May 09, 2006 | Permit Approved | 
| Jun 26, 2006 | Land Evidence Date | 
| Jun 26, 2006 | Phone Call | 
| Nov 29, 2006 | RIDEM Approval required | 
| Oct 03, 2007 | Correspondence Received |