| Action Date | Action Description | 
|---|---|
| Jun 07, 2006 | Assent Application Received | 
| Jun 08, 2006 | Administrative Review for Completeness | 
| Jun 14, 2006 | Additional Information Received | 
| Jun 15, 2006 | Application Accepted | 
| Jun 15, 2006 | Team Review for Completeness | 
| Jun 29, 2006 | HPHC Historical Preservation No Effect | 
| Sep 26, 2006 | Biologist Report | 
| Sep 26, 2006 | Engineering Report | 
| Sep 27, 2006 | Typist for Processing | 
| Sep 27, 2006 | Executive Sign Off | 
| Sep 27, 2006 | Sent to Photo Copy | 
| Sep 27, 2006 | Permit Approved | 
| Nov 03, 2006 | Land Evidence Date | 
| Aug 17, 2009 | Extension of Permit Request | 
| Aug 27, 2009 | Enforcement Compliance Inspection Required | 
| Sep 03, 2009 | Process Extension | 
| Sep 03, 2009 | Extension Approved |