| Action Date | Action Description | 
|---|---|
| Sep 12, 2006 | Assent Application Received | 
| Sep 13, 2006 | Administrative Review for Completeness | 
| Sep 20, 2006 | Deficient Application - Owner Notification Sent | 
| Sep 25, 2006 | Deficient Application Picked Up | 
| Sep 27, 2006 | Deficiency Response Received | 
| Oct 02, 2006 | Deficient Application - Owner Notification Sent | 
| Oct 02, 2006 | Deficient Application Picked Up | 
| Nov 08, 2006 | Deficiency Response Received | 
| Nov 09, 2006 | Administrative Review for Completeness | 
| Nov 09, 2006 | Team Review for Completeness | 
| Nov 09, 2006 | Application Accepted | 
| Nov 15, 2006 | Engineering Report | 
| Nov 15, 2006 | Typist for Processing | 
| Nov 15, 2006 | Executive Sign Off | 
| Nov 15, 2006 | Sent to Photo Copy | 
| Nov 15, 2006 | Permit Approved | 
| Nov 21, 2006 | HPHC Historical Preservation No Effect | 
| Nov 28, 2006 | Land Evidence Date |