| Action Date | Action Description | 
|---|---|
| Feb 11, 2008 | Assent Application Received | 
| Feb 11, 2008 | Administrative Review for Completeness | 
| Feb 12, 2008 | Team Review for Completeness | 
| Feb 12, 2008 | Team Review for Completeness | 
| Feb 12, 2008 | Application Accepted | 
| Feb 12, 2008 | Category A* (Docks) | 
| Feb 15, 2008 | HPHC Historical Preservation No Effect | 
| Feb 26, 2008 | 30 day Public Notice Issued | 
| Mar 27, 2008 | Public Notice End Date | 
| Apr 22, 2008 | US Army Corp of Engineers Permit Date | 
| Apr 24, 2008 | US Army Corps of Engineers Approval Received | 
| Apr 29, 2008 | Typist for Processing | 
| Apr 29, 2008 | Executive Sign Off | 
| Apr 29, 2008 | Sent to Photo Copy | 
| Apr 29, 2008 | Permit Approved | 
| Apr 29, 2008 | Biologist Report | 
| Apr 29, 2008 | Engineering Report | 
| May 19, 2008 | Land Evidence Date | 
| Jun 19, 2008 | Commencement of Work Notice received |