| Action Date | Action Description | 
|---|---|
| Jan 23, 2009 | Assent Application Received | 
| Jan 26, 2009 | Administrative Review for Completeness | 
| Jan 29, 2009 | Team Review for Completeness | 
| Jan 29, 2009 | Team Review for Completeness | 
| Jan 29, 2009 | Deficient Application - Owner Notification Sent | 
| Feb 13, 2009 | Deficiency Response Received | 
| Feb 13, 2009 | Administrative Review for Completeness | 
| Feb 16, 2009 | Team Review for Completeness | 
| Feb 16, 2009 | Team Review for Completeness | 
| Feb 16, 2009 | Application Accepted | 
| Mar 19, 2009 | HPHC Historical Preservation No Effect | 
| Mar 19, 2009 | HPHC Historical Preservation No Effect | 
| Mar 25, 2009 | Biologist Report | 
| Mar 25, 2009 | Engineering Report | 
| Mar 25, 2009 | Typist for Processing | 
| Mar 25, 2009 | Executive Sign Off | 
| Mar 25, 2009 | Sent to Photo Copy | 
| Mar 25, 2009 | Permit Approved | 
| Mar 27, 2009 | Land Evidence Date | 
| Sep 02, 2009 | Commencement of Work Notice received |