| Action Date | Action Description | 
|---|---|
| Sep 16, 2009 | Assent Application Received | 
| Sep 16, 2009 | Administrative Review for Completeness | 
| Sep 18, 2009 | Team Review for Completeness | 
| Sep 18, 2009 | Team Review for Completeness | 
| Sep 18, 2009 | Application Accepted | 
| Sep 18, 2009 | Category A* (Docks) | 
| Sep 22, 2009 | 30 day Public Notice Issued | 
| Oct 09, 2009 | Plans Received | 
| Oct 09, 2009 | HPHC Historical Preservation No Effect | 
| Oct 22, 2009 | Public Notice End Date | 
| Nov 19, 2009 | Engineering Report | 
| Nov 23, 2009 | Biologist Report | 
| Nov 23, 2009 | Typist for Processing | 
| Nov 23, 2009 | Executive Sign Off | 
| Nov 23, 2009 | Sent to Photo Copy | 
| Nov 23, 2009 | Permit Approved | 
| Dec 17, 2009 | Land Evidence Date | 
| Dec 23, 2009 | US Army Corps of Engineers Approval Received | 
| Jun 08, 2010 | Commencement of Work Notice received |